Veröffentlichungsdatum: 6 August 2012
Projektträger – zwischengeschaltetes Finanzinstitut
SLOVENSKE ELEKTRARNE ASOrt
Beschreibung
9-year investment programme mainly in renewable power generation focusing on overhauling/refurbishment and capacity expansion of the promoter's hydro power plant portfolio.
Ziele
The project concerns an investment programme, comprising approximately 100 schemes, which relate primarily to the overhaul/refurbishment of existing hydro power stations as well as capacity expansion with new small run of river hydro units - up to around 3.5MW in capacity. The project schemes will be dispersed throughout the Slovak Republic.
Sektor(en)
Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)
EUR 60 million
Gesamtkosten (voraussichtlicher Betrag)
EUR 120 million
Umweltaspekte
Considering their technical characteristics, the programme schemes fall under Annex II of the EIA Directive (2011/92/EU), and consequently it is the responsibility of the competent authority to determine the need for an Environmental Impact Assessment (EIA). Given the nature of the project schemes (overhaul/refurbishment of existing hydro, small run of river construction) it is expected that the vast majority of the schemes will not require an EIA.
Auftragsvergabe
The Bank will require the promoter to ensure that contracts for the implementation of the project have been/shall be tendered in accordance with the relevant applicable EU procurement legislation (Dir 2004/17/EC), with publication of tender notices in the EU Official Journal, as and where appropriate.
Projektstatus
Unterzeichnet - 2/09/2013
Haftungsausschluss
Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).