Veröffentlichungsdatum: 10 Juli 2009
Projektträger – zwischengeschaltetes Finanzinstitut
London Array is sponsored by E.ON, DONG Energy and Masdar
Ort
Beschreibung
The project is the 1st phase of an envisaged 1,000 MW offshore wind farm off the UK coast. Phase 1 will consist of 175 turbines and have a capacity of 630 MW.
Ziele
The project aims at helping the UK to achieve its ambitious target of electricity consumption based on renewable energy sources in 2020.
Sektor(en)
Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)
GBP 1 000 million.
Gesamtkosten (voraussichtlicher Betrag)
Indicatively estimated by the Bank at around GBP 2 200 million.
Umweltaspekte
By virtue of its technical characteristics the project is classified as an Annex II-project according to the EIA-Directive 85/337/EEC, as amended. A comprehensive EIA was conducted including a detailed biodiversity assessment. Planning approval was granted by the competent authority following extensive public consultation.
Auftragsvergabe
The promoter is not subject to EU procurement directives (Utilities Directive 2004/17) for the purchase of the project’s equipment as the concession to build an offshore wind farm was granted following a competitive tender (Round 2) launched by the UK government.
Projektstatus
Unterzeichnet - 8/06/2010