    Referenz: 20090001
    Veröffentlichungsdatum: 29 Juni 2009

    Projektträger – zwischengeschaltetes Finanzinstitut

    Scottish and Southern Energy Plc

    Ort

    Beschreibung

    The Project concerns the construction, commissioning and operation of six onshore wind farms with installed capacity amounting to nearly 650 MW. The six project schemes are in various phases of construction and their combined energy output may make up to around 1.5 GWh energy annually.

    Ziele

    The development of wind energy capacity will support EU and national targets for renewable energy generation and contribute to environmental and security of energy supply objectives. Electricity generation from onshore wind farms can produce electricity with substantially lower environmental impacts, particularly GHG emissions.

    Sektor(en)

    Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)

    GBP 400 million.

    Gesamtkosten (voraussichtlicher Betrag)

    GBP 925 million.

    Umweltaspekte

    The project sub-schemes would fall under Annex II of Directive 85/337/EEC, as amended by Directives 97/11/EC and 2003/35/EC. Thus, the project schemes are subject to an EIA based on a case-by-case decision or defined criteria set by the competent authorities. Permits have been granted for all project schemes and EIAs have been undertaken where required by the competent authority. The Bank will review the EIAs in detail during appraisal, including mitigating/compensation measures to be taken and any effects on nature conservation sites (Habitats Directive 92/43/EEC and Natura 2000).

    Auftragsvergabe

    The Promoter is not subject to EU Procurement Directives. In line with its principles and its statute the Bank will however ensure that suitable procurement procedures, including an appropriate selection of works, goods and services offered at competitive prices will be applied by the promoter and/or the special purpose companies.

    Projektstatus

    Unterzeichnet - 29/03/2010

    Haftungsausschluss

    Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
    Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).