    Referenz: 20080414
    Veröffentlichungsdatum: 31 Oktober 2008

    Projektträger – zwischengeschaltetes Finanzinstitut

    RTE EDF Transport S.A.

    Ort

    Beschreibung

    The project consists of a 4-year investment programme (2008-2011), comprises 31 schemes for reinforcing and extending the promoter’s transmission electricity network throughout France.

    Ziele

    The main purpose of the project is to cater for demand growth while improving efficiency and reliability of supply and to provide for connection of traditional and renewable generation resources.

    Sektor(en)

    Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)

    Up to EUR 400 million.

    Gesamtkosten (voraussichtlicher Betrag)

    EUR 1 149 million.

    Umweltaspekte

    Some schemes of the project involving long 400 kV and 225 kV overhead lines will fall under Annex I of the EIA Directive (85/337/EC and amendments), while the remainder will fall under ANNEX II, leaving it to the national competent authority to decide whether an EIA would be required in line with the screening criteria specified in the directive. The impacts that can be typically expected for such project schemes relate to visual impact, vegetation clearance, electromagnetic fields, noise nuisance, and disturbance during construction. The specific requirements of the French environmental legislation and the promoter’s application thereof will be investigated during appraisal. This includes addressing potential negative impacts on sites of nature conservation.

    Auftragsvergabe

    EIB will require the promoter to ensure that contracts for the implementation of the project have been/shall be tendered in accordance with the relevant applicable EU procurement legislation, including publication of tender notices in the Official Journal of the EU as and where appropriate.

    Projektstatus

    Unterzeichnet - 29/01/2009

    Haftungsausschluss

    Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
    Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).

    Tags

    Frankreich Energie