Veröffentlichungsdatum: 5 August 2008
Projektträger – zwischengeschaltetes Finanzinstitut
FH Campus WienOrt
Beschreibung
The project involves the construction of a new Campus for the University of Applied Sciences in Vienna to replace the existing facilities currently scattered across the city on eight different sites.
Ziele
It is foreseen to double the existing capacity on the new site to up to 4 000 students.
Sektor(en)
Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)
EUR 30 million.
Gesamtkosten (voraussichtlicher Betrag)
EUR 65 million.
Umweltaspekte
Universities are not specifically mentioned in the EIA Directive on Environmental Impact Assessment, though the project is covered by Annex II of the Directive in relation to urban development. The Bank’s services will verify during appraisal the EIA screening decision of the Competent Authority.
Auftragsvergabe
The Bank will require the promoter to ensure that all relevant contracts for the implementation of the project have been or shall be tendered in accordance with the relevant EU procurement legislation. The detailed procurement issues will be studied during appraisal.
Projektstatus
Unterzeichnet - 10/12/2009