    Referenz: 20080333
    Veröffentlichungsdatum: 18 September 2008

    Projektträger – zwischengeschaltetes Finanzinstitut

    OGK-5 JSC
    Contact person: Mr Luca Sutera, OGK-5 Chief Financial Officer

    Ort

    Beschreibung

    Upgrade of the Nevinnomyssk GRES power plant in Southern Russia, including the rehabilitation of existing generating capacity and building of a modern, efficient Combined Cycle Gas Turbine (CCGT) unit to replace two old gas-fired steam units.

    Ziele

    The project aims to increase energy efficiency and to promote the differentiation of energy supply as well as operational safety of the energy infrastructure.

    Sektor(en)

    Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)

    Up to EUR 250 million.

    Gesamtkosten (voraussichtlicher Betrag)

    Approximately EUR 500 million (including construction of the CCGT as well as rehabilitation of existing generating capacity).

    Umweltaspekte

    Due to its size and technical characteristics, the project requires an Environmental Impact Assessment (EIA) under EIB guidelines. The EIA process has been initiated and its review will form part of the Bank's appraisal of the project. The project is expected to contribute to meeting growing electricity demand with a lower environmental impact than other fossil fuel based alternatives.

    Auftragsvergabe

    The rehabilitation component of the project is expected to be procured under a number of separate works, supply and services contracts using mainly international tendering procedures. The new CCGT plant will be procured under a single Engineering, Procurement and Construction (EPC) contract. CCGT plant procurement has been initiated by OGK-5 under RAO UES public procurement practices, and the procurement has been completed after privatisation of the company.

    Projektstatus

    Unterzeichnet - 26/03/2010

    Haftungsausschluss

    Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
    Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).

    Tags

    Russische Föderation Energie