Veröffentlichungsdatum: 13 Oktober 2009
Projektträger – zwischengeschaltetes Finanzinstitut
Société Nationale Industrielle et Minière (SNIM)
Ort
Beschreibung
Construction of a new iron ore enrichment plant with a capacity of 4m t/year, extension of an existing mine and modernisation and extension of the ancillary facilities.
Ziele
The project will enable SNIM to increase its iron ore concentrate production capacity, thereby helping it to consolidate its position on the world market.
Sektor(en)
Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)
EUR 75 million
Umweltaspekte
An environmental and social impact assessment and a number of supplementary studies were conducted. The key impacts were properly identified and addressed. These concern water supply, air quality and the health of workers. Mitigating measures are set out in the respective management plans. The project's residual impact is therefore considered acceptable by the Bank.
Auftragsvergabe
Operating on the highly competitive global iron ore market, SNIM is subject to private sector procurement rules. The promoter applies procedures that comply with the Bank’s Guide to Procurement and are considered to be satisfactory by the EIB.
Projektstatus
Unterzeichnet - 1/12/2009
Haftungsausschluss
Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).