    Referenz: 20070435
    Veröffentlichungsdatum: 6 Mai 2009

    Projektträger – zwischengeschaltetes Finanzinstitut

    Kenya Electricity Transmission Company (KETCo)

    Ort

    Beschreibung

    Construction of a 450 km long 400 kV double-circuit power transmission line from Mombasa to Nairobi, construction of a 19 km 220 kV double-circuit line in Nairobi area, and expansion of substations in both Nairobi and Mombasa.

    Ziele

    The project is primarily intended to transfer power generated in the coast area to the main load centre around Nairobi, the capital. The Government of Kenya’s electrification target is to add 1 million consumers to the grid over the next 5 years. This will require substantial investments in both generation and transmission. Substantial new thermal generation capacity is planned in Mombasa. The project is designed to evacuate this new power capacity to Nairobi.

    Sektor(en)

    Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)

    EUR 60 million.

    Gesamtkosten (voraussichtlicher Betrag)

    EUR 214 million.

    Umweltaspekte

    Due to the project’s characteristics, the Kenyan legislation requires an environmental impact assessment. A consultant has therefore prepared an EIA report which identifies a number of issues such as the vicinity of a national park and the need of moving up to 280 households. Public consultations have highlighted the need for adequate and timely compensation of affected people. The environmental authority has issued its approval of the project.

    Auftragsvergabe

    Procurement of supplies envisaged to be financed by the EIB will be in line with the Bank’s Guide to Procurement to which the promoter is familiar. Other contracts will also be tendered internationally, in line with the rules of the other lenders involved.

    Projektstatus

    Unterzeichnet - 21/12/2009

    Haftungsausschluss

    Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
    Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).

    Tags

    Kenia Energie