Veröffentlichungsdatum: 29 Januar 2009
Projektträger – zwischengeschaltetes Finanzinstitut
Empresa de Transmisión Eléctrica Dominicana
Ort
Beschreibung
Extension of high voltage transmission network with 138 kV lines and substations in the South-western region of the Dominican Republic.
Ziele
The reinforcement of the transmission system will be designed to accommodate the development of other renewable energy projects in the region. The project will cover peak electricity demand and it is part of an integrated plan for the electricity sector in the country.
Sektor(en)
Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)
EUR 35 million.
Umweltaspekte
The Bank will verify that the impact of the project is in line with the EU and the Bank’s principles and standards as regards environmental and social issues.
Auftragsvergabe
The Promoter will comply with the Bank’s procurement guidelines when tendering contracts proposed for part-financing by the Bank.
Projektstatus
Unterzeichnet - 1/11/2010
Haftungsausschluss
Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).