    Referenz: 20060091
    Veröffentlichungsdatum: 9 August 2006

    Projektträger – zwischengeschaltetes Finanzinstitut

    EirGrid plc

    Ort

    Beschreibung

    Upgrading of the national electricity dispatch and control centre for operation of the electricity transmission network, including the purchase of necessary software and hardware, system configuration and consulting services.

    Ziele

    The project will promote the integration of the electricity transmission networks in Ireland and Northern Ireland, which include areas designated as objective 1. The project will support the establishment of the Single Electricity Market for the island of Ireland and will facilitate cross-border trading of electricity, and improve efficiency and security of supply. These benefits are consistent with the EU objectives to promote the interconnection and interoperability of trans-European energy networks and to support the management and rational use of energy.

    Kommentar(e)

    Electricity, gas and water supply.

    Sektor(en)

    Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)

    Up to 50% of the project costs.

    Gesamtkosten (voraussichtlicher Betrag)

    About EUR 52 million. Some cost variations possible depending on the exact timetable for the project’s implementation.

    Umweltaspekte

    The project does not come under the Environmental Directive (85/337/EEC as amended by 97/11/EC). The project has minimal environmental impact as its main components are IT hardware/software at the existing National Control Centre based in Dublin. Any structural changes or additional buildings for the project will be subject to the normal planning/consents from national and local authorities.

    Auftragsvergabe

    The Promoter has confirmed that contracts for the implementation of the project have been/shall be tendered in accordance with the relevant applicable EU procurement legislation (Dir 93/38/EEC as amended by 2004/17/EC), with parallel publication of tender notices in the Official Journal of the EU as and where appropriate. The specific procedures will be further evaluated by EIB.

    Projektstatus

    Unterzeichnet - 21/12/2006

    Haftungsausschluss

    Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
    Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).

    Tags

    Irland Energie