Veröffentlichungsdatum: 25 Mai 2005
Projektträger – zwischengeschaltetes Finanzinstitut
Egyptian Natural Gas Co., CairoOrt
Beschreibung
The project consists of two high-pressure pipeline sections from El Tina to Abu Sultan (62 km) and from Dashour to El Kureimat (88 km).
Ziele
The objective is to strengthen the gas transmission system in view of the increasing gas demand in the country.
Sektor(en)
Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)
EUR 50 million.
Gesamtkosten (voraussichtlicher Betrag)
EUR 102 million.
Umweltaspekte
The two pipelines are planned mainly to cross desert zones, as well as some agricultural and residential areas. The Bank has requested the promoter to carry out formal environmental impact assessments, which will be reviewed during appraisal.
Auftragsvergabe
The Bank will require the promoter to tender contracts to be financed by EIB in accordance with the Bank’s principle procurement rules, with which the promoter is familiar, including international competitive tendering with publications in the Official Journal of the EU.
Projektstatus
Unterzeichnet - 6/07/2005