Veröffentlichungsdatum: 20 Juni 2003
Projektträger – zwischengeschaltetes Finanzinstitut
City of MunichOrt
Beschreibung
The project consists in the refurbishment, reconstruction and extension of the sewage infrastructure in Munich between 2002 and 2005.
Ziele
The project will contribute substantially to modernise, develop and reinforce the environmental infrastructure of the City of Munich. The City of Munich is engaged to achieve sustainability in the Isar water floods area through best practice policies and infrastructure in waste-water management. The investments aim to realize this goal.
Kommentar(e)
Construction.
Sektor(en)
Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)
Up to EUR 90 million.
Gesamtkosten (voraussichtlicher Betrag)
Estimated at about EUR 260 million.
Umweltaspekte
It is not expected that the project will have any impact on Nature Conservation and Habitat areas. Environmental Impact Assessments (EIA) have been engaged by the promoter as requested by the national environmental legislation.
Auftragsvergabe
The promoter follows the German procurement guidelines, which are in line with EU procurement directives.
Projektstatus
Unterzeichnet - 1/07/2004
Haftungsausschluss
Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).