    Referenz: 20020367
    Veröffentlichungsdatum: 17 Juli 2002

    Projektträger – zwischengeschaltetes Finanzinstitut

    SEEBOARD Powerlink LimitedForest GateBrighton RoadCrawley RH11 9BHUKContact Point: James O'Sullivan

    Ort

    Beschreibung

    SEEBOARD Powerlink received an EIB loan for the first phase of its capex programme in the London Underground Power project, which involved the upgrading and renewal of London Underground's electricity transmission and distribution systems. Due to an amplification of the original work scope, a second capex programme is to be launched which includes incremental project works such as traction substations, non-tractions works, and power supplies for the ConnectPFI. The Promoter seeks EIB funding for this second phase.

    Ziele

    By renewing the sub-transmission and distribution systems, the project will contribute to meeting electricity demand growth on the London underground light railway system, reduce operation, maintenance and energy consumption costs, and improve the quality and reliability of electricity supply.

    Kommentar(e)

    Urban Environment

    Sektor(en)

    Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)

    Up to GBP 46 million.

    Gesamtkosten (voraussichtlicher Betrag)

    Estimated to be about GBP 93 million.

    Umweltaspekte

    The project is classified under Annex II of Council Directive 85/337 as amended by Directive 97/11/EC, thus not requiring a formal EIA process. Directive 97/11/EC has been fully incorporated in the UK's Town and Country Planning (Environmental Impact Assessment) (England and Wales) Regulations 1999. Environmental impact of the project is expected to be minimal given the nature of the proposed works.

    Auftragsvergabe

    The programme falls under the Procurement Directive 93/38/EC and its amendment 98/4/EC. The promoter has confirmed to fully comply with its requirements.

    Projektstatus

    Unterzeichnet - 27/11/2002

    Haftungsausschluss

    Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
    Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).

    Tags

    Vereinigtes Königreich Energie