Veröffentlichungsdatum: 8 Mai 2002
Projektträger – zwischengeschaltetes Finanzinstitut
Ministry of TransportOrt
Beschreibung
The project consists of a multi-annual investment program for upgrading of the railway infrastructure. Most of the project components are located along core rail routes within the TINA network and constitute necessary rehabilitation of priority lines. Project components are expected to be co-financed by ISPA.
Ziele
The proposed upgrading of the Slovenian rail network along main corridors V and X would help shifting traffic to environmentally friendly rail transport and would help Slovenia cope with additional traffic expected between the EU and Slovenia while meeting EU standard requirements.
Sektor(en)
Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)
Loan of up to EUR 60 million
Gesamtkosten (voraussichtlicher Betrag)
Estimated at approximately EUR 103 million
Umweltaspekte
There are no known environmental concerns at this stage as the works are essentially rehabilitation and upgrading of the existing priority network and thus fall outside Annexes I and II of the 97/11/EC Directive.
Auftragsvergabe
Tendering will comply with the Bank's rules.
Projektstatus
Unterzeichnet - 18/11/2003