Übersicht
The construction and operation of several small and medium size Hydro Electric Power Plants with an expected installed capacity of more than 900 MW. The plants are either run of river or they have reservoir’s smaller than 15 square kilometres.
Support the development of renewable energy resources in Turkey and further develop the country’s hydro power potential.
If the project were located in the EU, it would fall under Annex II of the EIA Directive (85/337/EEC) as amended, requiring the competent national authority to determine the need for an EIA. In this case, as the installed capacity for each plant – except for two small run of river developments – is likely to exceed 50MW, they will require an EIA under national legislation.
Publication in the OJEU will be undertaken for items financed by the EIB, in line with the EIB Guide to Procurement.