Link zum projekt
Datenblätter
Andere Links
Übersicht
Veröffentlichungsdatum
5 August 2004
Projektstatus
Referenz
Unterzeichnet | 04/12/2006
20040279
Projekttitel
Projektträger – Finanzintermediär
Electrabel - Castelnou Energía SL
ELECTRABEL
General Castaños no 4 - 3a planta
E - 28004 MADRID
Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)
Gesamtkosten (voraussichtlicher Betrag)
EUR 145 m
Approximately EUR 330 m
Beschreibung
Ziele
Design, construction, commissioning and operation of an 800 MWe natural gas fired combined cycle gas turbine power station (CCGT) located near Zaragoza (Objective 2 area).
The project will meet growing electricity demand on the Iberian Peninsula at a competitive cost using modern gas-fired combined-cycle technology with a relatively low environmental impact.
Umweltaspekte
Auftragsvergabe
Compliance with EU environmental directives and national laws shall be ensured.
Procurement procedures are in compliance with relevant EU directives and national and regional legislation.