    Referenz: 20180244
    Veröffentlichungsdatum: 25 September 2018

    Projektträger – zwischengeschaltetes Finanzinstitut

    ACCEPTABLE CORPORATE(S)

    Ort

    Beschreibung

    Programme loan (PL) concerns the financing of medium to large greenfield on-shore wind and solar projects in Spain, awarded in the renewable energy auctions that took place in 2017. The auctioned wind and solar capacity will boost the country effort to meet the EU 2020 targets to achieve 20% of gross final consumption of energy from renewable energy sources. In addition, it will complement the electricity system in view of the expected closure of up to 5GW of domestic coal-fired capacity by 2020 and the shutdown of nuclear capacity during the next decade.

    Ziele

    The programme, financed under the EIB climate action, will contribute to achieve Spain 2020 targets to reduce CO2 emissions, by financing renewable energy sources. Furthermore, it will also boost economic and social cohesion.

    Sektor(en)

    Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)

    EUR 131 million

    Gesamtkosten (voraussichtlicher Betrag)

    EUR 900 million

    Umweltaspekte

    The sub-projects will go through an Environmental and Social Impact Assessment (ESIA) process, including a public consultation, and EIB will make sure that the Environmental Impact Statements will be issued and approved, as necessary. The applicability of the Environmental Impact Assessment (EIA) Directive 2011/92/EU, the Strategic Environmental Assessment (SEA) Directive 2001/42/EC, the Habitats Directive 92/43/EEC and the Birds Directive 79/409/EEC will also be reviewed at the appraisal for each of the eligible subprojects.

    Auftragsvergabe

    Spain has now incorporated two of the latest EU Directives for Procurement (EU Directives 2014/23/UE and 2014/24/UE). The Spanish national law 9/2017 transposes the two Directives mentioned, this law entered into force in early March 2018. Accordingly, all subprojects under the PL are expected to follow this new Spanish law 9/2017 that transposes the two latest procurement EU Directives mentioned above. EIB services are in the process of carrying out due diligence on this matter.

    Projektstatus

    Genehmigt - 18/09/2018

    Haftungsausschluss

    Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
    Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).

    Tags

    Spanien Energie