Referenz: 20170483
Veröffentlichungsdatum: 31 Januar 2018

Projektträger – zwischengeschaltetes Finanzinstitut

STOCKHOLMS LAENS LANDSTING

Ort

Beschreibung

Construction of three extensions of the Stockholm metro with a total length of 19.6 km and 11 underground stations.

Ziele

The project consists of three separate deep underground line extensions to the Stockholm Metro. The extensions are for Arenastaden (4.1 km of track with 3 stations), Barkarby (4 km with 2 stations) and Nacka och Söderort (11.5 km with 6 stations).

Sektor(en)

Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)

SEK 7750 million (EUR 747 million)

Gesamtkosten (voraussichtlicher Betrag)

SEK 26574 million (EUR 2562 million)

Umweltaspekte

The project falls under Annex II of the EIA Directive 2011/92/EU and may therefore require Environmental Impact Assessments (EIA). The promoter is also required to declare that the project has no negative impact on an area forming part of the Natura 2000 network (falling under the Habitats Directive 92/43/EEC or Birds Directive 79/409/EEC, as amended by Directive 2009/147/EC).

Auftragsvergabe

The Bank will require the promoter to ensure that contracts for the implementation of the project have been/shall be tendered in accordance with the relevant applicable EU procurement legislation (Directives 2004/18/EC and/or 2004/17/EC as well as Directives 89/665/EEC and 92/13/EEC) as interpreted by the Court of Justice of the EU, with publication of tender notices in the Official Journal of the European Union (OJEU), as and where required.

Projektstatus

Unterzeichnet - 26/06/2018

Haftungsausschluss

Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The data provided on this page is therefore indicative and cannot be considered to represent official EIB policy (see also the Explanatory notes).

Tags

Schweden Verkehr