Veröffentlichungsdatum: 21 September 2005
Ort
Beschreibung
Replacement of an existing combined heat and power plant (TEC-2) in Riga, Latvia (Objective 1 Area). The installation comprises a gas-fired combined cycle unit, heat recovery steam generator and steam turbine with an anticipated net power output of approximately 400 MWe.
Ziele
To raise the reliability and efficiency of energy supply in Latvia, and meeting environmental policy objectives.
Sektor(en)
Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)
EUR 40 million. The EIB has submitted its financing proposal for EUR 40 million in July 2005 to Latvenergo following a public procurement tender. Latvenergo is expected to publish the results of the tender by year-end 2005.
Gesamtkosten (voraussichtlicher Betrag)
Approximately EUR 200 million.
Umweltaspekte
The project will be located in a lightly inhabited industrial area east of the city on the site of the existing plant. Environmental Impact Assessment (EIA) was conducted in line with EU Directives and national law.
Auftragsvergabe
Procurement procedures are in compliance with relevant EU directives and national and regional legislation.
Projektstatus
Unterzeichnet - 15/12/2005
Haftungsausschluss
Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).