Veröffentlichungsdatum: 30 Juli 2004
Projektträger – zwischengeschaltetes Finanzinstitut
Public Establishment of Electricity for Generation and Transmission (PEEGT).Ort
Beschreibung
Construction and operation of a dual-fired greenfield power generating plant, which consists of a base load Combined Cycle Gas Turbine (CCGT) unit of 750 MWe some 25 km south of Damascus.
Ziele
The project aims at the cost-effective supply of electricity, both in terms of a growing demand and re-establishing security of supply. In addition, the combined cycle gas turbine technology will contribute to lowering emisions of greenhouse gases and air polluants per unit of electricity generated.
Sektor(en)
Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)
EUR 200 million.
Gesamtkosten (voraussichtlicher Betrag)
Estimated at some EUR 415 million.
Umweltaspekte
An Environmental Impact Assessment (EIA) is currently being prepared for the project. The project is expected to comply with both national standards and international recommendations in the field of environment. Due to its technology, the project is expected to provide electricity with low environmental impact.
Auftragsvergabe
International procurement, in line with EIB guidelines.
Projektstatus
Unterzeichnet - 1/11/2004
Haftungsausschluss
Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).