Veröffentlichungsdatum: 11 August 2003
Projektträger – zwischengeschaltetes Finanzinstitut
Planta de Regasificación de Sagunto, SA.Ort
Beschreibung
The project consists of the design, construction, commissioning and operation of a LNG (Liquefied Natural Gas) import terminal in the extension of the Mediterranean industrial port of Sagunto some 18 km north of Valencia.
Ziele
The project will contribute to meeting gas demand growth and diversifying gas imports to the Iberian Peninsula. The LNG terminal will receive LNG shipments and deliver natural gas to the regional/national gas transmission grids.
Kommentar(e)
LNG (Liquefied Natural Gas).
Sektor(en)
Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)
Up to 75% of project cost.
Gesamtkosten (voraussichtlicher Betrag)
EUR 350-400 million.
Umweltaspekte
The project is classified under Annex I of the Environmental Impact Assessment (EIA) Directive (85/337/EEC as amended by 97/11/EC), and also under the Seveso II directive (EC 96/082) on the prevention of major accidents for projects involving dangerous substances. The promoter has carried out a fully-fledged EIA including public consultation, and obtained the formal approval from the Ministry of Environment in November 2002 (“Declaración de Impacto Ambiental”).
Auftragsvergabe
In accordance with Directive 93/38/EC, the promoter has advertised for the main turnkey project's construction contract in the EC Official Journal.
Projektstatus
Unterzeichnet - 14/07/2004