Veröffentlichungsdatum: 29 April 2002
Projektträger – zwischengeschaltetes Finanzinstitut
Red Eléctrica de España, S.A.Ort
Beschreibung
The project consists of a range of measures for expanding and reinforcing the promoter's electricity transmission network.
Ziele
The project comprises a large number of geographically dispersed schemes on the Spanish transmission network throughout the country. The capacity being added over the two-year period includes high voltage substations, overhead lines and underground cables. Approximately 50% of the investments will benefit Objective 1 Assisted Areas, the remaining being located in Objective 2 Assisted Areas (40%) and non-assisted areas (10%).
Kommentar(e)
Electricity transmission
Sektor(en)
Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)
Up to 40% of project cost
Gesamtkosten (voraussichtlicher Betrag)
Approximately EUR 500 mio
Umweltaspekte
The promoter is expected to follow the EU directive concerning preparation of Environmental Impact Assessments. In this project, it is possible that some schemes fall under Annex I of the EIA Directive – to be verified during appraisal.
Auftragsvergabe
The promoter is required to respect the Community Directives as regards invitations to tender (directive 93/38/EC).
Projektstatus
Unterzeichnet - 26/11/2002
Haftungsausschluss
Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).