    Referenz: 20130190
    Veröffentlichungsdatum: 5 September 2013

    Projektträger – zwischengeschaltetes Finanzinstitut

    ASFINAG AUTOBAHNEN- UND SCHNELLSTRASSEN-FINANZIERUNGS AG

    Ort

    Beschreibung

    The project is part of ASFINAG’s 2013-2018 tunnel safety investment programme. It is located on the A9 Pyhrn motorway between Linz and Graz and is subdivided into 3 major schemes: (i) upgrading from 1 to 2 tubes of a chain of 4 tunnels (the so-called Klaus sector), (ii) upgrading from 1 to 2 tubes of the Bosrucktunnel, (iii) upgrading from 1 to 2 tubes of the Gleinalmtunnel.

    Ziele

    The national tunnel safety investment programme aims at complying with the EU Tunnel and Road Safety Directives in general and at improving road safety in Austria.

    Sektor(en)

    Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)

    EUR 400 million

    Gesamtkosten (voraussichtlicher Betrag)

    EUR 800 million

    Umweltaspekte

    During appraisal the Bank will verify the compliance of the investments composing the project with the EIA Directive 2011/92/EU, Habitats Directive 92/43/EEC and Birds Directive 79/409/EEC as and where appropriate.

    The impact of Directive 2004/54/EC on road safety in tunnels, as amended by Regulation (EC) No 596/2009 of the European Parliament and of the Council of 18 June 2009 and the Directive 2008/96/CE on road safety, will be verified as well.

    Auftragsvergabe

    The project’s compliance with the applicable EU procurement legislation (Directives 2004/17/EC/ or 2004/18/EC and 2007/66/EC) will be checked during appraisal, in particular with respect to the publication of the tender notices in the EU Official Journal as and where appropriate. Details of the procurement strategies will be reviewed during appraisal.

    Projektstatus

    Unterzeichnet - 12/12/2013

    Haftungsausschluss

    Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
    Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).

    Tags

    Österreich Verkehr