    Referenz: 20120602
    Veröffentlichungsdatum: 18 September 2013

    Projektträger – zwischengeschaltetes Finanzinstitut

    ZESCO Ltd

    Ort

    Beschreibung

    The transmission component consists of the construction/upgrading of 100 km transmission lines on 132 kV voltage and of seven 132-330 kV transmission substations. The distribution component comprises the upgrading of the 11-33 kV distribution system with nine 11-33 kV distribution substations and some 200 km of distribution lines and underground cables.

    Ziele

    The purpose of the project is to reinforce and upgrade the power transmission and distribution infrastructure in the Lusaka area. The proposed investment programme will help remove bottlenecks from the current aged power network, thus reducing equipment failure and electricity losses. The project will increase the reliability and quality of domestic power transmission and distribution service in the Lusaka area.

    Sektor(en)

    Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)

    EUR 78 million

    Gesamtkosten (voraussichtlicher Betrag)

    EUR 189 million

    Umweltaspekte

    132 kV transmission lines of this program would fall under definition of EIA directive 2011/92/EU Annex 2 (if situated within EU), and would require the competent Environmental Agency to screen and decide the necessity of ESIAs. The promoter has prepared the ESIA for these 132 kV works. Other works of the project (11 and 33 kV distribution) are not expected to require ESIAs.

    Auftragsvergabe

    The Bank will require the promoter to ensure that implementation of the project will be done in accordance with the Bank’s Guide to Procurement.
    The procurement packages are envisaged to be defined considering parallel co-financing with World Bank.

    Projektstatus

    Unterzeichnet - 16/01/2015

    Haftungsausschluss

    Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
    Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).

    Tags

    Sambia Energie