Suche starten De menü de ClientConnect
Suche starten
Ergebnisse
Top-5-Suchergebnisse Alle Ergebnisse anzeigen Erweiterte Suche
Häufigste Suchbegriffe
Meistbesuchte Seiten
    Referenz: 20070057
    Veröffentlichungsdatum: 27 April 2007

    Projektträger – zwischengeschaltetes Finanzinstitut

    Orkuveita Reykjavikur (Reykjavik Energy (RE)).

    Ort

    Beschreibung

    Part-financing of the expansion of Hellisheidi Geothermal Power Plant in the south-west of Iceland.

    Ziele

    Electricity generated by the project will be used mainly for industrial purposes, in particular to meet demand from aluminium smelters, as well as for serving commercial and industrial consumers in the Reykjavik area. The project will also generate hot water, which will be carried by pipeline to the Reykjavik area for space heating in the industrial and domestic sectors. The project is in line with the Bank's objectives for supporting renewable energy and the rational use of energy.

    Kommentar(e)

    Electricity.

    Sektor(en)

    Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)

    Approximately EUR 140 million.

    Gesamtkosten (voraussichtlicher Betrag)

    Approximately EUR 280 million.

    Umweltaspekte

    The project has been subjected to a full Environmental Impact Assessment (EIA) in accordance with national legislation, which is based on EU Directives 85/337 and 97/11 (the project falls under Annex II of Directive 97/11). The EIA has been approved by the Planning Agency after seeking public consultation and the opinions of the relevant competent authorities.

    Auftragsvergabe

    The procedures employed for awarding works, supplies and services contracts for the various components of the project are in accordance with Icelandic legislation, which is based on the relevant EU Directive (2004/17/EC) and includes the requirement to publish tender announcements in the EC Official Journal. In general, the promoter of this project applies open procedures for works and supply contracts, while specialised services for drilling and engineering services are awarded following negotiated procedures.

    Projektstatus

    Unterzeichnet - 16/07/2007

    Haftungsausschluss

    Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
    Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).

    Tags

    Island Energie