    € 82,100,000
    Countries
    Sector(s)
    Morocco : € 82,100,000
    Energy : € 82,100,000
    Signature date(s)
    16/11/2016 : € 32,100,000
    22/12/2014 : € 50,000,000
    (*) Including a € 32,100,000 Investment Grants provided by the NEIGHBOURHOOD INVESTMENT PLATFORM

    Summary sheet

    Release date
    18 June 2014
    Status
    Reference
    Signed | 22/12/2014
    20130468
    Project name
    Promoter - financial intermediary
    OUARZAZATE III (TOWER)
    MOROCCAN AGENCY FOR SOLAR ENERGY
    Proposed EIB finance (Approximate amount)
    Total cost (Approximate amount)
    EUR 82 million
    EUR 855 million
    Location
    Sector(s)
    • Energy - Electricity, gas, steam and air conditioning supply
    Description
    Objectives

    Construction and operation of a 150 MW concentrating solar power (CSP) Tower plant under the third phase of the Ouarzazate solar power complex.

    The project's main objective is to help developing a globally-available, non-carbon power generation technology that ultimately may not require fossil fuel back-up capacity and reduce the costs of CSP for world benefit. By creating a new green industry and increasing the penetration of renewable energy in the country's energy mix, the project will contribute to Morocco's objectives of a more secure energy supply, energy diversification, CO2 emission reductions, increased employment, and protecting the local environment.

    Environmental aspects
    Procurement

    If the project were located in the EU, it would fall under Annex II of the Environmental Impact Assessment (EIA) Directive (85/337/EEC) as amended, requiring the competent national authority to determine the need for an EIA. Under Moroccan Law, the project requires a mandatory EIA including initial scoping and public consultation. During appraisal, the Bank will ensure that the project complies with the Bank's principles and standards as regards environmental and social issues.

    Within the EU, the promoter, being a public contracting authority, would be subject to public procurement procedures according to 2004/17/EU, including publication of contract notices in the Official Journal of the EU. In line with the Bank's principles and its statute, the promoter is following the provisions of the Bank's Guide to Procurement, which includes amongst others international competitive bidding and Official Journal of the EU contract notice publication for the items to be financed by the Bank.

    Under ELM Guarantee
    Comments

    This operation is covered by the ELM Guarantee.

    This operation is covered by the EU Guarantee for EIB loans outside the EU.

    Disclaimer

    Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The information and data provided on this page are therefore indicative.
    They are provided for transparency purposes only and cannot be considered to represent official EIB policy (see also the Explanatory notes).

    Documents

    Environmental and Social Data Sheet (ESDS) - OUARZAZATE III (TOWER)
    Publication Date
    12 Mar 2016
    Document language
    Main Topic
    Lending
    Document Number
    53800243
    Document Focus
    Environmental Information
    Project Number
    20130468
    Sector(s)
    Countries
    Publicly available
    Download now
    Environmental and Social Impact Assessment (ESIA) - OUARZAZATE III (TOWER) - Framework ESIA for Ouarzazate I, II & III
    Publication Date
    21 Apr 2016
    Document language
    Main Topic
    Lending
    Document Number
    53830098
    Document Focus
    Environmental Information
    Project Number
    20130468
    Sector(s)
    Countries
    Publicly available
    Download now
    Non-Technical Summary (NTS) - OUARZAZATE III (TOWER) - Nooro III Tower CSP Plant
    Publication Date
    16 Apr 2016
    Document language
    Main Topic
    Lending
    Document Number
    57981755
    Document Focus
    Environmental Information
    Project Number
    20130468
    Sector(s)
    Countries
    Publicly available
    Download now
    Other links

    General enquiries and comments

    The EIB is committed to open communication and encourages constructive stakeholder input regarding its activities.
    Enquiries and comments concerning the EIB’s involvement in a project or the financing facilities, activities, organisation and objectives of the EIB, can be sent to the EIB Infodesk.
    Alternatively, the EIB can be contacted through its external offices.
    Queries regarding details of a specific project, in particular when it is under appraisal by the EIB, should preferably be addressed directly to project promoters.

    Media enquiries

    Media-related enquiries can be addressed to the EIB Press Office. Please also visit our Media information section.

    Complaints mechanism

    Any complaint regarding alleged maladministration can be lodged via the EIB Complaints Mechanism. The European Ombudsman acts as an independent external accountability mechanism of the EIB.

    Zero tolerance against fraud and corruption

    The EIB has a zero tolerance policy on fraud or corruption. To report allegations of fraud and corruption relating to EIB-financed projects, please contact the Investigations Division. All reports will be treated as strictly confidential and handled in line with EIB investigation procedures and the EIB Group Anti-Fraud Policy.

    Related publications