    The project aims at the renewal and expansion of the promoter's distribution networks, reducing energy losses and enhancing the reliability and quality of electricity supply in the states of Sao Paulo and part of Mato Grosso do Sul. The project will connect some 116 000 customers to the network, of which over 39 000 are low income.

    Objectives

    The project complies with the External mandate as it supports economic infrastructure, social inclusion and poverty alleviation, while supporting EU presence in Latin America through the transfer of know-how.

    Comments

    This operation is covered by the EU Political Risk Guarantee for EIB loans outside the EU.

    Sector(s)

    Proposed EIB finance (Approximate amount)

    EUR 115 million

    Total cost (Approximate amount)

    EUR 238 million

    Environmental aspects

    If located in the EU, the project would fall under Annex II of Directive 85/337/EEC and its amendments, requiring the component authority to determine whether an EIA is required. Normally ElAs would not be expected given the focus on medium and low voltage networks, whose impacts are related to visual nuisance, vegetation clearance and disturbances during construction. The local environmental assessment rules, biodiversity and social impacts have been assessed during appraisal and the promoter's capacity to address them is good.

    Procurement

    The Bank will require the promoter to ensure that implementation of the project will be done in compliance with the Bank's Guide to Procurement.

    Status

    Signed - 8/04/2013

    Disclaimer

    Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The information and data provided on this page are therefore indicative.
    They are provided for transparency purposes only and cannot be considered to represent official EIB policy (see also the Explanatory notes).

    Related tags

    Brazil Energy