    Reference: 20030577
    Release date: 23 April 2007

    Promoter – Financial Intermediary

    ANAS S.p.A.

    Location

    Description

    Construction of a 32-km dual 3-lane (2x3), toll motorway by-passing the City of Mestre, designed to flank an existing and highly congested road by-pass.

    Objectives

    The project forms part of the trans-European network (TEN-T) providing the main East - West motorway corridor across Northern Italy from Milan to Udine. It is expected to substantially improve the flow of passengers and freight traffic through the area by providing the extra capacity needed close to Mestre.

    Sector(s)

    Proposed EIB finance (Approximate amount)

    EUR 350 million.

    Total cost (Approximate amount)

    EUR 750 million.

    Environmental aspects

    The project falls under Annex I of the EIA directive, making an environmental impact appraisal mandatory. The EIA procedures and resulting documentation will be reviewed during appraisal.

    Procurement

    Following a formal tender process, a consortium led by the Italian construction conglomerate Impregilo has been awarded the EPC contract for the project. The project has been tendered according to the specific 'General Contractor' provisions defined in the "Legge Obiettivo" 443/2001.

    Status

    Signed - 9/06/2011

    Disclaimer

    Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The information and data provided on this page are therefore indicative.
    They are provided for transparency purposes only and cannot be considered to represent official EIB policy (see also the Explanatory notes).

    Related tags

    Italy Transport