    Reference: 20160690
    Release date: 16 December 2016

    Promoter – Financial Intermediary

    KONINKRIJK DER NEDERLANDEN

    Location

    Description

    The project consists of the construction of a 2x3 lanes motorway of approximately 4.2km, incorporating below river and land based tunnels. The project also includes lowered connections to the A20 motorway and elevated connections to the A15 motorway. The project is situated near the city of Rotterdam, the Netherlands.

    Objectives

    The Blankenburg project is located on the comprehensive TEN-T road network. The project aims to increase capacity and improve road safety on sections of the Dutch motorway near Rotterdam and underlying road network with heavy traffic, and is being procured as a design-build-finance-maintain (DBFM) public-private partnership (PPP).

    Comments

    The total project cost is estimated at approximately EUR 1 bn.

    Sector(s)

    Proposed EIB finance (Approximate amount)

    EUR 328 million

    Total cost (Approximate amount)

    EUR 904 million

    Environmental aspects

    The project consists of a new 2x3 motorway 4.2 km long, connecting two existing motorways (A15 and A20), therefore it falls under Annex I of the EIA Directive 2011/92/EU. Compliance with the EIA Directive, the Habitats Directive (92/43/EEC) and Birds Directives (79/409/EEC) and NATURA 2000 will be verified in detail during appraisal.

    Procurement

    The tender process was launched in May 2016, 3 letters of interest were then received in June 2016, and in July 2016 a Competitive Dialogue process started with the bidders. Final offers and Contract award together with Financial Close are expected to happen during 2017. The Concession will include design, construction, financing, and maintenance. Procurement procedures and compliance with Directive 2004/18/EC will be verified in detail during appraisal.

    Status

    Signed - 17/10/2018

    Disclaimer

    Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The information and data provided on this page are therefore indicative.
    They are provided for transparency purposes only and cannot be considered to represent official EIB policy (see also the Explanatory notes).

    Related tags

    The Netherlands Transport