    Reference: 20150825
    Release date: 28 July 2016

    Promoter – Financial Intermediary

    Private Company

    Location

    Description

    The project is an investment programme that comprises investment schemes in the production and distribution of electricity in Styria, Austria. The electricity generation scheme includes plans to build a 16 MW hydropower plant in the city of Graz and a 39 MW wind farm located in the mountainous region of Deutschlandsberg, together with their grid connection facilities. The electricity distribution part covers extensions and refurbishments of the low- and medium- voltage electricity distribution grid in Styria.

    Objectives

    The hydropower and wind power plants in the project will contribute to national and EU renewable energy targets. The network investment programme aims to improve the quality and the reliability of grid infrastructure.

    Sector(s)

    • Energy - Electricity, gas, steam and air conditioning supply

    Proposed EIB finance (Approximate amount)

    EUR 140 million

    Total cost (Approximate amount)

    EUR 333 million

    Environmental aspects

    The project is an expansion of a distribution electricity network and construction of a new hydroelectric power generation plant and a wind farm in Styria, Austria. The project falls under Annex II of the EIA Directive 2011/92/EU. Here, the competent authority in line with Austrian environmental law (UVP-G 2000) requested an Environmental Impact Assessment (EIA) including public consultation for a wind farm and hydroelectric power plant. The final environmental permits were granted for both. Electricity distribution at medium and low voltage, are typically implemented with low or insignificant environmental impact. The environmental impact of all the projects will be further appraised.

    Procurement

    The European Commission has exempted the generation of electricity in Austria from public procurement provisions by Decision 2008/585/EC. The Bank will review the project's procurement procedures to ensure that its funds are used appropriately for the purchase of works, goods and services.

    Status

    Signed - 31/03/2017

    Disclaimer

    Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The information and data provided on this page are therefore indicative.