TAFILA WIND FARM
- Reference: 20110433
- Release date: 13 November 2012
Jordan Wind Project Company PSC (Jordan)
- Jordan
The project comprises the construction and operation of a greenfield wind Independent Power Producer (IPP) to produce 117 MW electricity in Jordan. The wind farm will be located in the Tafila Governorate of Jordan, in an area east of the town of Ghurandil and north of the Lafarge Rashidiya cement plant. The electricity generated will be sold to the National Electricity Power Company (“NEPCO”).
The project will contribute to Jordan's development objective in the energy sector aiming to increase both electricity production and the share of renewable energy in its electricity generation portfolio. It will contribute to climate change mitigation, thereby displacing fossil fuel-based generation and avoiding greenhouse gas emissions. The project also fulfils the Government's objective of increasing the participation of the private sector in energy generation.
- Energy
EUR 49 million
Total cost (Approximate amount)EUR 195 million
Environmental aspectsThe project (including the wind farm connection to the grid) is undergoing an EIA according to the local legislation which will also include public consultation. No resettlement of local population is envisaged. The project site is located less than 5 km away from the Dana Biosphere Reserve’s Eastern border and overlaps with an Important Bird Area. Detailed biodiversity surveys to assess the potential impact on these protected areas and species should be concluded by the end of the year. Compliance with the principles of the EU EIA Directive and the EU Habitats and Birds Directive shall be verified during the appraisal.
The attached ESIA is the version submitted to the national competent authorities for the national administrative process and consultation. This does not include EIB's comments nor those of the consultation which will be taken into account in the final draft and which will be published as soon as finalised.
The promoter has followed a public procurement process for a turn-key Design-Build-Operate-Maintain (DBOM) contract for the wind farm in line with the Bank's procurement guidelines. Contract award and signature is expected for end 2012.
Under appraisal - 13/11/2012.
- 28-01-2013 - Environmental and Social Impact Assessment (ESIA) EN
Disclaimer
Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. Therefore data provided on this page is indicative and cannot be considered to represent official EIB Policy (see also the Explanatory notes).