    Promoteur – Intermédiaire Financier

    Enel Green Power S.p.A.

    Lieu

    Description

    Financing of the investment programme of Enel Green Power Romania for the development, construction and operation of three on-shore wind farms located in the regions of Dobrogea (Salbatica and Corugea) and Banat (Moldova Noua) for a total installed capacity of some 260 MW.

    Objectifs

    The project concerns the development, construction and operation of three Romanian wind farms with a total capacity of 258 MW: Salbatica 1 (70 MW), Salbatica 2 (70 MW), Moldova Noua (48MW) and Corugea (70MW). The projects will be equipped with 126 turbines with a unit capacity ranging from 2.0 to 2.3 MW and hub height between 95 and 101m. Furthermore each project will include the electrical grid to connect the different wind turbines, the civil works for foundations and infrastructure (e.g. access roads) as well as the substation and HV cable for the connection to the network.

    Secteur(s)

    Montant BEI envisagé (montant approximatif)

    EUR 200 million

    Coût total (montant approximatif)

    EUR 400 million

    Aspects environnementaux

    The projects fall under Annex II of the EIA Directive 85/337/EC (as amended) and have been screened in by the national competent authorities which have required a full EIA including public consultation. According to the information available all project sites, located in the Dobrogea and Banat regions, may either be inside or close to Natura 2000 sites.  During the appraisal the Bank will check whether the EIAs have been carried out in compliance with the EU Directives and in particular whether the competent environmental authority has performed an appropriate assessment of the impacts (including cumulative ones) of the wind farms on the affected protected natural sites as envisaged under the EU Habitats Directive.

    Passation des marchés

    Since the promoter is a public undertaking it will follow the EU Procurement Directive 2004/17/EC to procure the equipment and construction works according to the public procurement principles established in the EIB guide to procurement.

    Statut

    Signé - 28/11/2013

    Clause de non-responsabilité

    Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.