Construction and operation of the Zimella - Cervignano pipeline (170 km, DN1400, 75 bar) and of an interconnection plant in Sergnano.
Construction and operation of the Poggio Renatico-Cremona pipeline (149 km, DN1200, 75 bar).
Objectives
The extension of the gas transmission system is necessary to increase gas flow flexibility in the transport system in the North Western part of Italy. The financing of this project contributes to the Bank’s lending policy on security of energy supply. The new pipelines meet the general criteria for Trans-European Energy Networks (TEN-E) projects of common interest set out under the TEN-E guidelines. Increasing penetration of gas in all sectors will displace less efficient and more polluting sources of energy, thereby contributing to European Community objectives of rational use of energy and environmental protection.
The pipeline schemes have been subject to environmental assessments as required by the EIA Directive 85/337/EC and amendments. Authorizations were granted by the competent authorities in 2009 for the Poggio Renatico-Cremona pipeline and in 2011 for Zimella - Cervignano pipeline.
Procurement
The investments under the project are subject to the procurement provisions defined in Directive 2004/17/EC for entities operating in the water, energy, transport and postal services sectors.
Status
Signed
-
18/07/2012.
Related Documents
12-10-2011 - Non Technical Summary (NTS) of the Environmental Impact Assessment (EIA) - Poggio Renatico - Cremona IT
12-10-2011 - Non Technical Summary (NTS) of the Environmental Impact Assessment (EIA) - Zimella - Cervignano IT
Disclaimer
Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The data provided on this page is therefore indicative and cannot be considered to represent official EIB policy (see also the Explanatory notes).
The EIB is committed to open communication and encourages constructive stakeholder input regarding its activities. Enquiries and comments concerning the EIB’s involvement in a project or the financing facilities, activities, organisation and objectives of the EIB, can be sent to the EIB Infodesk.
Alternatively, the EIB can be contacted through its external offices.
Queries regarding details of a specific project, in particular when it is under appraisal by the EIB, should preferably be addressed directly to project promoters.
The EIB has a zero tolerance policy on fraud or corruption. To report allegations of fraud and corruption relating to EIB-financed projects, please contact the Fraud and Investigation division. All complaints will be treated as strictly confidential and handled in line with the EIB investigation procedures and the Anti-Fraud Policy.
The EIB is committed to achieving the highest possible level of transparency. The EIB Transparency Policy sets out how the EIB discloses information and consults with its stakeholders so as to promote better awareness and understanding of its strategies, policies and operations.