SAV/SITAF Opere Autostradali
- Reference: 20040539
- Release date: 10 February 2005
Contact point: Dott. M. Christillin, Direttore,
1024 Chatillon (AOSTA) - Strada Barat 13
Tel. 0166/560411 SITAF
Contact point: Ing. Bernardo Magrì, Direttore,
10059 Susa (To) - Fraz. San Giuliano 2
Tel. 0122 621 615
- Italy
- Piemonte & Val D’Aosta.
Upgrading to new environmental and safety standards of two TENs: the A 32 highway Torino-Bardonecchia, including the Frejus Tunnel (giving access to France) and the A5 Torino-Aosta - Gran San Bernardo Tunnel (giving access to Switzerland).
Improve driving and safety conditions on two TENs connecting Italy’s North-West, the country’s largest industrialized area, to France and Switzerland.
- Transport
EUR 160 million
Total cost (Approximate amount)EUR 400 million
Environmental aspectsDue to its nature the project should be beneficial to the environment. However motorway construction, or upgrading, is subject to the requirements of EU Directive 07/11/CE, Annex 1. Documents will be checked during appraisal.
SAV and SITAF have concession agreement with ANAS, state company. Conformity with EU procurement regulations is going to be assessed.
Signed - 20/06/2005.