    Reference: SG/E/2011/11
    Received Date: 23 September 2011
    Subject: Belgrade Bypass
    Complainant: Individual on behalf of property owners
    Allegations: Allegedly unfair expropriation without prior consultation and adequate/mutually agreed compensation
    Type: E - Environmental and social impacts of financed projects
    Outcome*: Areas for improvement
    Suggestions for improvement: yes
    Admissibility*
    Assessment*
    Investigation*
    Dispute Resolution*
    Consultation*
    Closed*
    23/09/2011
    1/11/2011
    1/12/2014
    25/03/2015
    25/03/2015

    * Admissibility date reflects the date the case was officially registered. All other dates pertain to the date in which a stage was completed.

    Project Information