    Reference: SG/A/2009/02
    Received Date: 24 February 2009
    Subject: Bujagali Hydroelectric Project
    Complainant: Association Sherpa
    Allegations: Access to the documents related to the “Bujagali Hydroelectric Project”
    Type: A - Access to Information
    Outcome*: Friendly solution
    Suggestions for improvement: yes
    Admissibility*
    Assessment*
    Investigation*
    Dispute Resolution*
    Consultation*
    Closed*
    24/02/2009
    1/04/2009
    6/05/2009
    3/06/2009

    * Admissibility date reflects the date the case was officially registered. All other dates pertain to the date in which a stage was completed.

    Case Description

    Complaint

    On 24 February 2009, Association Sherpa submitted a complaint with the EIB Complaints Mechanism (EIB-CM) challenging the fact that the relevant services of the EIB had unjustly rejected its request for access to a number of documents concerning a dam project in Bujagali.

    EIB-CM Action

    The EIB-CM has performed an assessment of the complaint.

    Conclusions and Recommendations

    The EIB-CM has concluded that the relevant services of the EIB should have dealt with the access request submitted by the complainant in accordance with the information provided in its report and recommends the disclosure of the required documents.