Reference: SG/P/2018/12/PR
Received Date: 20 August 2018
Subject: Nepal Power System Expansion
Complainant: Confidential
Allegations: Irregularities during the tender procedure
Type: P - Procurement
Suggestions for improvement: no
Admissibility*
Assessment*
Investigation*
Dispute Resolution*
Consultation*
Closed*
31/08/2018
3/09/2018
18/09/2018
* Admissibility date reflects the date the case was officially registered. All other dates pertain to the date in which a stage was completed.
Case Description
Nepal Power System Expansion